Paul/Adrian,
The RFQ for the above package has now been published via CTM and includes all contract documents including Works Information documentation but excluding supporting WI documentation such as SLP’s, drawings and method statements etc. (this supporting information was provided a number of weeks ago via the Employers doc controller).
We have provided the option to further discuss Price requirements however the estimated value and lack of design scope makes an Option A Fixed Cost the likely and most economical choice.
We have allowed ample time (six-weeks) to enable you to submit a compliant bid in the first instance; taking cognisance of previous RFI’s issued by the Employer. Additionally prior to submission I suggest that we arrange a time and place to allow you to present your bid thus making certain that potential impact to time as a result of clarifications is properly mitigated.
Deadline of clarification questions – 30/10/2018
Response deadline - 21/11/2018
If you have any further questions then please do not hesitate to contact me or the Project Manager Virag Szabo.